Determine how many people are needed to complete a given amount of work within a specified number of days.
A certain job
PeopleThat is
Daysto complete
The same job
DaysHow many people are needed to finish it?
Amount of Work Person-days
Number of People People
(1) Workload = Number of days taken × Number of people
(2) Number of people needed = Workload ÷ Number of days to complete the work