Work Calculation (How Many Days Will It Take?)

Manage Bookmarks
This calculates the number of days required to complete a given amount of work with a specified number of workers.
A certain job
PeopleThat is
Days...is completed
The same task
PeopleHow many days will it take to complete this task?
Workload Person-days
Number of Days Required Days
(1) Workload = Number of days taken × Number of workers
(2) Number of days required = Workload ÷ Number of workers